49.2 MWp
installed capacity
41 MW
grid capacity
61.1 GWh
expected annual output
49.5 ha
dual-use site (solar + agriculture)
Romgaz's first solar park, planned at Zagăr in southern Mureș County, with 49.2 MWp installed capacity on a 49.5 ha dual-use agri-solar site. The EPC tender is valued at €47.4 million.
Overview
- Romgaz's first solar park, planned at Zagăr, in southern Mureș County.
- Romgaz is Romania's largest natural gas producer, state-controlled and listed on the Bucharest Stock Exchange.
- 49.2 MWp installed capacity, 41 MW grid capacity and 61.1 GWh expected annual output.
- 49.5 ha dual-use site, combining solar generation and agriculture.
- EPC tender valued at €47.4 million. Grid connection through a new 20/110 kV substation.
- Third Romgaz energy asset in the county, after the Iernut power plant and the Azomureș chemical platform.