430 MW
combined-cycle capacity (2 × 215 MW)
56%
gross electrical efficiency
€325 million
project value
A new 430 MW combined-cycle gas power plant built by Romgaz at Iernut, with two 215 MW blocks and 56% gross electrical efficiency. Construction is over 90% complete, with grid synchronisation scheduled for the end of 2026.
Overview
- New 430 MW combined-cycle gas plant built by Romgaz at Iernut, on the Mureș river.
- Two identical 215 MW blocks with six GE turbines (four gas, two steam).
- 56% gross electrical efficiency, 20% higher than conventional thermal plants.
- Dry Low NOx combustion within EU emission limits, black start capability and a direct 110/220/400 kV grid connection.
- Project value of €325 million. Construction is over 90% complete, under TÜV Austria supervision. Grid synchronisation is scheduled for the end of 2026.