A multifunctional innovation, business, culture and public-space development on an underused plot in central Târgu Mureș, next to the Theatre and the Small Theatre. It combines about 5,000 m² of innovation space, 2,000 m² of retail and over 400 underground parking spaces, with an estimated investment of €16.1 million.
The project
The site is an underused plot in the city centre. It sits next to the Theatre and the Small Theatre, close to Piața Trandafirilor. The building follows a curved line around a public garden with green terraces. An elevated pedestrian promenade runs on the roof.
It links the Theatre, the hotel and the surrounding streets without barriers. Three underground levels hold the parking, with EV charging stations. The parking connects directly to the promenade and the Theatre.
- Innovation: offices, co-working, labs, multipurpose hall for exhibitions and events
- Business: flexible office space, retail and café units
- Culture: direct connection to the Theatre and the Small Theatre, rooftop space for events
- Community: public garden, stepped green terraces, outdoor event areas
Location
- ~150,000 inhabitants in Târgu Mureș
- 1 km to A3 motorway (as stated in the brochure)
- 1.5 km to city centre
- 1 km to the medical hub
Public space
The elevated promenade has terraces, gardens and cafés. It offers views towards the historic centre. Stepped green terraces form an open-air seating area for cultural events. Landscaped paths link the Theatre, the hotel and the nearby streets. All routes are barrier-free.
Estimated investment costs
Based on the general estimate (SF / DALI). The estimate is indicative and does not include VAT, specialised IT equipment or furniture. Costs are based on 2024–2025 average market prices in Romania.
- Cap. 1 Land and site organisation: €550,000
- Cap. 2 Utilities and connections: €380,000
- Cap. 3 Design and technical assistance: €1,020,000
- Cap. 4 Construction works (Innovation Centre + underground parking): €12,500,000
- Cap. 5 Other costs (permits, studies, etc.): €180,000
- Cap. 6 Contingencies (10%): €1,460,000
- Total investment (estimated): ≈ €16,100,000
Expected impact
The project adds about 5,000 m² of green and public space in the city centre. Parking moves underground, which frees surface space for pedestrians. Offices and labs create jobs in services and research. Theatre audiences and office users bring daily traffic to local shops and restaurants. The site connects to public transport and cycling routes.