A regional colocation data center with a dedicated hall for AI workloads and high-performance computing, owned by Mureș County Council in partnership with Mureș Industrial Park. It is approved for financing under the Just Transition Fund programme.
Project profile
- Type of project: regional colocation data center with a dedicated hall for AI workloads and high performance computing (HPC)
- Ownership type: public (Mureș County Council), in partnership with Mureș Industrial Park
- Investment: 231M RON (€44.1M)
- Site area: 15,020 sqm
- Technical capacity: 2.5 MW installed in total, of which 2 MW standard colocation; up to 200 racks across two data halls of approx. 322 sqm each
- Design standard: Tier III, in line with TIA-942, EN 50600 and BICSI-002; target PUE 1.35
- AI and HPC capacity: 0.5 MW in a separate hall, served by direct liquid cooling (rear door heat exchangers and coolant distribution units) on a high temperature loop at 25/35°C, sized for high density racks
- Services: data processing, storage and colocation for companies in the industrial park and the wider region
- Status: approved to be financed under JTF Program, estimated construction period up to 20 months
Site and latest decisions
The data centre will be built in Sânpaul village, inside Mureș Industrial Park, on a plot free of buildings with cadastral number 53181 and an area of 15,020 m², next to the Târgu Mureș–Războieni railway, about 2 km from the E60 road and close to Transilvania International Airport. The works cover 9,947 m² of the plot: the data centre building of 1,687 m² (27 × 61 m, 7.9 m high), an access control post, internal roads, eight parking spaces, concrete platforms for generators, transformers and chillers, a fire-water tank and green areas.
In July 2026 Mureș County Council approved the feasibility study (prepared by Modern CM) and Scenario 1, with a total value of 231,170,529.96 lei including VAT, of which 91,813,278.11 lei for construction and installation. Implementation is estimated at 20 months, of which 14 months of works. In September 2026 the county announced that the project had won funding of almost 240 million lei.
Sources: Mureș County Council, specialist report no. 19962 of 10 July 2026 (PDF); Cuvântul Liber, 29 September 2026.