News · 9 November 2026
Romgaz expects Iernut power plant in commercial operation by mid-2027
Romgaz deputy director Aristotel Jude said the 430 MW Iernut plant could connect to the national grid in early 2027 and start commercial operation around mid-2027.

Aristotel Jude, deputy general director of Romgaz, said the Iernut power plant could be synchronised with the National Energy System in the first quarter of 2027 and enter commercial operation around mid-2027. He spoke on Monday at a Focus Energetic conference on the 2026-2027 winter, as reported by AGERPRES via Punctul.ro.
Jude said Romgaz now acts as general contractor after contractual problems with the former contractor. Most of the contracts needed to start production are signed and under way, he said. A memorandum approved by the Government in May allowed negotiation without prior publication.
He argued that, under Law 99/2016 on sectoral procurement, no Romanian state company would soon be able to build a plant of this size. He also said Romgaz invests over RON 5 billion a year, with an execution rate above 80%.
According to the report, the new Iernut thermal power plant has an installed capacity of 430 MW and a combined-cycle gas turbine technology. Its gross electrical efficiency is 56.4%. The Ministry of Energy said the plant also has a Black Start system, which allows it to restart without external grid power.